Home » RDBMS Server » Server Administration » How to use DBMS_SCHEDULER ??
How to use DBMS_SCHEDULER ?? [message #199512] Tue, 24 October 2006 22:22 Go to next message
vx_2004
Messages: 10
Registered: July 2006
Junior Member
I am having issues in scheduling a stored proc from Oracle.

I want to run that stored proc every 10 minutes. This is what I am doing :


1) Create a schedule

Begin
dbms_scheduler.create_schedule(
schedule_name=>'DENORM_DELTA_SCHEDULE',
start_date=>'24-OCT-2006 10:10:00.000001 PM -05:00',
repeat_interval=>'FREQ=MINUTELY;INTERVAL=10',
end_date=>null);
end ;


2) Then I am creating a program :

begin
dbms_scheduler.create_program (
program_name=>'DENORM_DELTA_PRG',
program_type=>'STORED_PROCEDURE',
program_action=> 'user.proc1',
enabled=> TRUE);
END;

3) Then finally I am creating program :

Begin
dbms_scheduler.create_job(
job_name=>'DENORM_DELTA_JOB',
program_name=>'DENORM_DELTA_PRG',
schedule_name=>'DENORM_DELTA_SCHEDULE',
enabled =>TRUE,
comments=> 'It updates Denorm tables needed for Reporting - Narendra Joshi');
end;
/


in Scheduler tables, it shows fine, only problem is data displayed.

Pls tell me what other steps are needed ??? or what I am missing ??







Re: How to use DBMS_SCHEDULER ?? [message #202916 is a reply to message #199512] Mon, 13 November 2006 05:04 Go to previous message
vjeedigunta
Messages: 201
Registered: March 2005
Location: Hyderabad
Senior Member

Not sure on the schedulers ..but why cant you just create a job which does the same ..

-Sai Jeedigunta